High School Building Renovation 
 
Dedication and ribbon cutting ceremony... September 2nd, 2010. 

as of August 28th... finishing touches and moving in!

as of August 16...

as of August 3rd...

Cabinetry has been installed.  Painting, staining and laying tile are underway.

as of July 15th...

Plumbing and electrical inspections were recently completed!  The high school is now almost all completely insulated.  Pending the insulation inspection, the sheet rocking will begin.

as of July 9th...

The electrical, HVAC and plumbing are done.  Next up are the insulation and sheetrock.

as of July 2nd...

The framing has been completed, along with the new roof, hallway and vaulted foyer.  Electrical cables and the plumbing are well under way.  Next up is the insulation and sheetrock for all of the classrooms.

as of June 17th...

Work is progressing very rapidly on the high school renovation. Demolition has been completed, and the new framing and sheetrock work are well under way. Electrical cables have been moved and the new footings have been poured. Next up is the framing for the foyer and hallway, as well as running the wiring throughout the building. Thank you for all of your help and prayers.
 